- ZEALLY BAY ROAD
Project Name: Zeally Bay Road Carpark Client: Surf Coast Shire Location: Zeally Bay Road, Torquay Dates: October 2020 to November 2020 Project Overview: Excavate existing crushed rock carpark and kerb Place new kerb and edge strip Build new road pavement with crushed rock Supply and place asphalt Line marking, signage installation Pram crossing and raised pedestrian crossings
- BLACK SATURDAY FIRE AND FLOOD RECOVERY CONTRACT
Client: Murrindindi Shire Council Dates: January 2010 to September 2012 Location: Various throughout Murrindindi Shire Project Overview: PatAsh were successful in their bid to win the Fire and Flood recovery work for Murrindindi Shire in 2010 – resulting from the Black Saturday Fires. PatAsh established operation yards at King Lake, Marysville, Flowerdale, Buxton and Molesworth, with the main command centre in King Lake. PatAsh actively recruited local employees and sub-contractors from the devastated areas. PatAsh was initially contracted to assist with the clean-up works including tree removal and disposal, erosion control, environmental clean-up, contamination control, debris clearing and swale excavation. From the initial clean up, PatAsh were contracted to rebuild town roads, install new drainage, and assist communities to rebuild. Our works included: Major road rehabilitations Road construction and reinstatement Bridge construction and repairs, and maintenance Major drainage line for Marysville Installation of culverts, including concrete pipes, headwalls, end walls, pits, grated pits Asphalt reinstatement and patching PatAsh also assisted the Murrindindi Council to establish hard rock quarries for council roads to be used by all contractors completing the works in the area.
- FLOOD RECOVERY WORKS
Client: Moira Shire Council Dates: October 2012 to October 2013 Location: Various throughout Moira Shire Project Overview: PatAsh and Civil were successful in their bid to win the Flood recovery work for Moira Shire in 2012. After award, PatAsh quickly established a local office to control the contract in Numurkah. PatAsh employed 100% local staff from the affected area, including truck drivers, plant operators and management teams. We also had a large subcontractor base who were all local to the area. All materials were sourced locally – quarry materials, concrete products, office equipment, mechanical parts and labour and accommodation. Our scope of works was as follows: Road reconstruction works Gravel road re-sheeting Construction of new gravel roads Bitumen reinstatement – patching program >8,000m2 Shoulder reconstruction Asphalt edge sealing Drainage Works Installation of new culverts Installation of new headwalls and wing walls Desilting of existing swale drains Rock beaching to bridges, culverts
- CHICKEN FARM TRUCK ENTRANCE
Client: Rob Collier Earthworks Dates: November 2014 to December 2014 Location: Bacchus Marsh-Geelong Road, Parwan Project Overview: Works on Vic Roads Road Road widening, Pavement construction Asphalting and Primer sealing Culvert Installation Traffic Management on Vic Roads
- WARRANDYTE SHARED PATH
Client: Manningham City Council Dates: May 2014 to June 2014 Location: Pound Road, Warrandyte Project Overview: Shared path construction including: Minor earthworks FCR pavement with Asphalt wearing course Traffic management Tree loping Line marking
- WEBB DOCK ROCK REVETMENT
Client: McConnell Dowell Dates: August 2015 to November 2015 Location: Webb Dock, Docklands Project Overview: Source and import approx. 10,000 tonnes hard rock Shape existing sub grade Place geofabric layer with help of scuba divers underwater Place armour rock and under layer rock Including high spec quality control and survey
- SHARED USER PATH – ARDEER & SUNSHINE
Client: Brimbank City Council Dates: November 2015 to November 2016 Location: Part of Regional Rail Link – From Tottenham Station to Western Ring Road Project Overview: Construction of 5.8km long, 3m wide concrete construction path as part of the Regional Rail Link Construct 17,000m2 concrete Shared User Path including 2500+m3 concrete and 1500 sheets of SL82 mesh Electrical works including Public lighting, including conduits and pits the whole length of the path, traffic light alterations and pedestrian crossings. Line marking, traffic management, drainage alterations, landscaping, garden bed cultivation, fencing installations, and culvert construction.
- REGIONAL TRAIN STATION PLATFORM REHABILITATIONS
Client: V Line Dates: November 2016 – December 2016 Location: Ardeer Station Rockbank Station Little River Station Corio Station North Shore Station Wandong Station Project Overview: Reconstruction of platform pavements, including excavation of existing surface, install base rock layer, and Asphalt wearing course. Platform Repairs – Undertake platform reconstruction works to 6 Regional V Line stations. Works include train and pedestrian management, implement train safety management plan, excavate existing surface, supply and lay class 1 FCR base, asphalt wearing course.
- GEELONG RING ROAD – TEMPORARY PAVEMENT WORKS
Client: Lend Lease Dates: 2 Stages of works – April 2015 to November 2016 Location: Pigdons Road Overpass on Geelong Ring Road Project Overview: Construction of temporary pavement for bridge rectification works, Excavation, Pavement construction, Asphalt, Wire rope removal and reinstatement, Drainage works, Removal of temporary pavement and reinstate topsoils swale 12 months after bridge works are complete.
- PIIOP PROJECT 2015 (PRIVATE IRRIGATION INFRASTRUCTURE OPERATORS PROGRAM)
Client: Murray Irrigation Limited Dates: May 2015 to August 2015 Location: Deninliquin, Finley and Berrigan – MIL Catchment Area Project Overview: Installation of Flume Gates and Slip Meters Major structural concrete works Retrofitting existing concrete structures Installation of aluminium walkways and handrails Quality and survey control to ensure accuracy in water metering
- PALM LAKES SUBDIVISION & WETLANDS CONSTRUCTION
Client: Palm Lake Works Dates: May 2016 to September 2016 Location: Palm Lakes Resort, Truganina Project Overview: Stage 4 Subdivision works Earthworks – cut and fill for concrete roads, and hose blocks Preparation for concrete roads Drainage Rock Breaking Wetlands Works Massive rock wall construction including footings, agi drainage, and backfilling Concrete shared paths Sediment pond constructions and water treatment areas
- 8.2KM OF ROAD RECONSTRUCTIONS – PORTARLINGTON
Clent: City of Greater Geelong Dates: November 2016 to December 2017 Location: Portarlington Project Overview: Reconstruction of 8.2km of residential road in North-East Portarlington. Excavation and disposal of 18000 cub m of spoil 50+ Pit alterations 120+ crossover culvert with driveable headwalls 16km of swale drains Kerb and channel and concrete driveways Road pavement construction including 20,000 ton class 3 and 20,000 ton class 2 rock 60,000 m2 of spray sealing, and asphalting.